Program A: Primary Water Wells-Storage-Treatment Site
PROJECT YEAR
Project: A.2
2025
Ground & Elevated Tank Construction
Dr. Shelton Viney Water Treatment Plant

The next phase of Project A will be to build tanks both on the ground and an elevated water tank. Storage is an important component to any water delivery system.
Procurement Phase:
Contractor:
Awarded
Garney
Project Status:
Date Started:
Date Completed:
Completed
1 de septiembre de 2025
30 de abril de 2026
Program A: Primary Water Wells-Storage-Treatment Site
Project: A.2
PROJECT YEAR
2025
Ground & Elevated Tank Construction
Dr. Shelton Viney Water Treatment Plant

The next phase of Project A will be to build tanks both on the ground and an elevated water tank. Storage is an important component to any water delivery system.
Procurement Phase:
Contractor:
Awarded
Garney
Project Status:
Date Started:
Date Completed:
Completed
1 de septiembre de 2025
30 de abril de 2026